Project Co-ordinator: Khalid Ashraf
Date: 19/2/2024
S.No | Project title | Status | Remarks by Khalid | Remarks by Sir Irfan |
1. | Ilham Website | Completed | Need to raise invoice of January | |
2. | Ilham WhatsApp Integration | Halted | Reminded to Sir but halted due to unknown reason | |
3. | Snowhite Dry Cleaners | Completed from our side | Client has some queries, meeting today at 11 | |
4. | Alwasila Revisions | 80% Completed | Two tasks remaining will be finalized today | |
5. | Newage Data Entry | 90% Completion | They have provided incomplete sheet with duplicate items otherwise this would have been completed | |
6. | Newage Remaining Website Development | Awaiting Details from their side. | ||
7. | WhatsApp Bulk Sender | 80% Completion | Due day extended till tomorrow Tuesday 20/2/2024 | |
8. | Alhabib Website | 80% | Whatever provided to me has been uploaded still incomplete because of lack of details, need to live website after checking work done till now. | |
9. | Dr. Saqib | 5% | Task assigned to Mahenoor, started working, need to review the strategy prepared by Mahenoor, alternative followups will be maintained | |
10. | Bloomo Facebook Marketing | Awaiting details to open an account in TCS and stock from their side, our work has been started. | ||
11. | Zivaah Implementation | 70% | System is ready and they are operating but some field adding tasks and report layout tasks has been assigned to Sarfaraz | |
12. | Kids Mania | 60% | Awaiting Product & Supplier List from their side. Report layout tasks will be assigned to Sarfaraz today | |
13. | SindhTV | 40% | ||
14. | Musab Fayyaz | Awaiting details to open an account in TCS |