Project Co-ordinator: Khalid Ashraf

Date: 19/2/2024

S.NoProject titleStatusRemarks by KhalidRemarks by Sir Irfan
1.Ilham WebsiteCompletedNeed to raise invoice of January
2. Ilham WhatsApp IntegrationHaltedReminded to Sir but halted due to unknown reason
3. Snowhite Dry CleanersCompleted from our sideClient has some queries, meeting today at 11
4. Alwasila Revisions80% CompletedTwo tasks remaining will be finalized today
5.Newage Data Entry90% CompletionThey have provided incomplete sheet with duplicate items otherwise this would have been completed
6.Newage Remaining Website DevelopmentAwaiting Details from their side.
7.WhatsApp Bulk Sender80% CompletionDue day extended till tomorrow Tuesday 20/2/2024
8.Alhabib Website80%Whatever provided to me has been uploaded still incomplete because of lack of details, need to live website after checking work done till now.
9.Dr. Saqib 5%Task assigned to Mahenoor, started working, need to review the strategy prepared by Mahenoor, alternative followups will be maintained
10. Bloomo Facebook MarketingAwaiting details to open an account in TCS and stock from their side, our work has been started.
11. Zivaah Implementation70%System is ready and they are operating but some field adding tasks and report layout tasks has been assigned to Sarfaraz
12.Kids Mania60%Awaiting Product & Supplier List from their side.
Report layout tasks will be assigned to Sarfaraz today
13. SindhTV40%
14. Musab FayyazAwaiting details to open an account in TCS