Front line Man: Abdul Latif

Implementation Person: Khalid Ashraf

Sales Coordinator: Hammad Khan

Start Date: 11/3/2024

Before Start Implementation Time as per Plan: 1 Month from the starting date excluding eid holidays , sundays and public holidays i.e., 17/3/24

Total Implementation with training: 3 Months

S.NoDateTasksStatusRemarks by KhalidRemarks by Sir Irfan
1.8/3/24Payment MadeCompleted
2.10/3/24Sunday Off
2.12/3/24 – 13/3/24NDA / TDA Signed
2. 15/3/24 – 22/3/24Domain CreationCompletedUsually take 3 days when we create on own domain but they want in their own domain name which was not clear from their end and they also want on their own cloudflare which was not clear in the first meeting.
3. 22/3/24 – 26/3/24System Testing Reports, Data, OptionsCompleted23rd March was off and 24th March was sunday
4. 26/3/24Report Setting task assignedTesting Two tasks remaining will be finalized today
5.27/3/24Videos Shared & Sales Order integrated from website but in testing one user created with sorted optionsDone
6.28/3/24Asked credentials for Courier
7.29/3/24Online Meeting with Abdul LatifDone
8.1/4/24Asked for API Access authentication which was to be sent by TCS to Ahsan Bhai on mail Not received email
9.3/4/24Complete Product Sync, Order Sync with Cron Job done and displayed on video meetingDone
10. 4/4/24Awaiting TCS Approval
11.4/4/24Bulk Dispatch OrdersDone

Final Remarks: Till we are done with your order integration process and final testing we recommend you to enter suppliers and expenses in the ERP which is not a part of synchronization process

Handover Date: 17/3/2024

Approved by:

Sir Irfan (CTO): Approval Pending

Sarfaraz (Developer): Approval Pending

Abdul Lateef: Approval Pending

Faheem Anis (Developer): Approval Pending

Khalid Ashraf: Approval Pending

Hammad Khan: Approval Pending