InCharge: Latif ur Rahman
Contact Person: +92 336 2055366
PROJECT DONE
Step | Start Dt | Days | Est Dt | Actual Dt | Remarks | Customers | |
Step 1 | payment | 01-03-2023 | 1 | DONE | |||
Step 2 | KYC | 02-03-2023 | DONE | ||||
Step 3 | Basic Setup | 02-03-2023 | DONE | ||||
Step 4 | Your Data | 02-03-2023 | DONE | ||||
Step 5 | Training | 02-03-2023 | DONE | ||||
Step 6 | Trial Run | 04-03-2023 | DONE | ||||
Step 7 | Go Live Preparation | 05-03-2023 | DONE | ||||
Step 8 | Parallel Run | ——— | DONE | ||||
Step 9 | Go Live | 06-03-2023 | 3 | DONE | |||
Total Plan days | |||||||
- no need of training because he was is using software
Status: