- Step 1: Please made a payment as per agreement for
- One Time Software Cost and
- Monthly Support Agreement Payment
- Step 2 KYC: we need following details from customer – Expected Customer Response Time: 1 week
- Compulsory Items
- Company Name:
- Company Address:
- Contact Person / Point of Contact for Software:
- Cell:
- Email:
- Product List (Finish Goods, Raw Material, Packing Material, Semi Finish Goods) in excel as per our format Download from Here
- Customer List in excel as per our format Download from Here
- Supplier List in excel as per our format Download from Here
- Your Country:
- Tax requirement (S/TAX / VAT) – for example all your invoice required tax option
- Godown: are you manging multiple Godowns or single Godown?
- Do you need virtual Godown / physical location / venue etc for managing Godown?
- Are you a wholesaler or retailer?
- Optional but recommended
- Soft copy of your logo
- Most of the time your printer or your designer can provide this
- Your current Invoice Copy
- Your current Receipt Format
- Any Other Document Printout e.g.
- Stock Transfer
- GRN
- PO
- SO
- DC
- Any Report which you are making in excel
- Copy of reports which are must (if any)
- Soft copy of your logo
- Optional
- users list – who are using the ERP / CRM / Software
- with their access rights or roles e.g., Accountant / Operator / Manager / Admin etc
- Chart of account as per our format
Download from Here- Banks List
- Expense List
- Godown List
- Employee List – for payroll module
- Stax / NTN
- users list – who are using the ERP / CRM / Software
- Compulsory Items
- Step 3 Basic Setup: We will setup your ERP: Expected Response Time: 3 Days
- Step 4 Your Data: we will import the information provided by you: Expected Response Time: 3 Days
- Step 5 Training: Training Sessions as per your agreement: Expected Duration 2 Weeks – Approx 3-4 Training Sessions
- Online Training on Any Desk
- Training on our premisses
- On Site Training
- Video Training
- Step 6 Trial Run: Trial Run – Expected Duration 4-6 Weeks
- Customer will require to check day to day activates and cross check reports with manual records or with old systems
- Step 7 Go Live Preparation: Go Live Preparation – Expected Duration 2-4 Weeks
- Customer will provide opening balances of
- their customers
- suppliers
- banks etc
- products / inventory
- Customer will provide opening balances of
- Step 8 Parallel Run: Parallel Live Run with existing system (Optional) 1-2 Months
- Step 9 Go Live: Go Live and close old system – only use them for old records