S.noClient StatusDeadline RemarksAction to be takenRemarks by Sir Irfan
1WhatsApp Bulk SenderAPI Completed, Angular 60% work done07/02/2024 2nd Online Meeting with Armaghan Team to be schedule on Monday after discussion with CARTZ Link team
2Ilham Website UpgradationTask other than 3d model has been assigned to Fahad Softco at 25K. 18/1/20243d Model reference has not been provided by Ilham Staff.
3Ilham Software link with WhatsAppAll relevant details has been sent & Discussed with Faheem. He gave me time for 2 weeks18/1/2024Awaiting link for review submission page on Shopify which will be provided by Fahad Softco
4* Al Wasila App DevelopmentDeployment done, Assigned to Ahmed code has not been checked yet nor the working on Payment Method has been started31/12/2023Critical it should be done by Khurram Bhai. Lack of Environment Setup. Laptop Challenges facing by Ahmed
5Sindh TV Website DevelopmentTheme Finalized, Assigned to Fahad Softco, Awaiting 50% payment from Sindh TV15/03/2024Payment will be done by Sindh TV on Monday